Location: Adelaide, South Australia
Client: Delta Group
Services: Strip-out, asbestos removal, lead remediation
Value: $0.4 Million
Duration: February – April 2021
Project Details
Hazmat remediation and strip out to a city block consisting of 6 multi-story buildings and a shopping centre off one of the highest trafficked streets in the Adelaide CBD.
Project Facts
- Remediation was completed with up to 18 Technicians on-site daily.
- 80+ tonnes of hazardous waste were removed from the site.
- Zero LTIs
- Work completed 11 days ahead of program.
![6](https://aztechservices.com.au/wp-content/uploads/elementor/thumbs/6-q96orvtkde9m99z38d9car3rai8ajeiijpdq2wjxjc.jpg)
![5](https://aztechservices.com.au/wp-content/uploads/elementor/thumbs/5-q96ort01sw5rag36ou1gl9tdicm6wb7bjbf9n2o420.jpg)
![4](https://aztechservices.com.au/wp-content/uploads/elementor/thumbs/4-e1675816007130-q96orq6j8e1wbm7a5atkvsizq70397w4ixgt78sako.jpg)
![7](https://aztechservices.com.au/wp-content/uploads/elementor/thumbs/7-q96orzkx4qerjptmmevukq5lo1pre6xfw7zo00ecug.jpg)
![3](https://aztechservices.com.au/wp-content/uploads/elementor/thumbs/3-q96ormf6h1wr16cqr972lth5cnimefh76euva4xv9k.jpg)
![2](https://aztechservices.com.au/wp-content/uploads/elementor/thumbs/2-q96orkji3du6dyfh28dtgty85vrvz19qi5jwbl0nm0.jpg)
![1](https://aztechservices.com.au/wp-content/uploads/elementor/thumbs/1-q96orhpzivqbf4jkip5xrcnudq5sbxyjhrlfvr4u4o.jpg)