Projects

Hydro Aluminium, Kurri Kurri, NSW

Location: Kurri ­Kurri, NSW
Client:
CMA Contracting
Services: Asbestos Remediation
Value: $0.5 Million
Duration: 2018-2019

Project Details

Aztech Services Australia was engaged by CMA Contracting to assist in the remediation of 24 sites owned by HAKK. The sites included contaminated residential properties, a disused municipal landfill and a stockpile site within HAKK.

Over 40,000 tonnes of Asbestos Contaminated Waste was remediated across the sites. The project required close consultation with SafeWork NSW to ensure the regulator’s expectations were met.

The sheer size of the project presented many challenges, Aztech Services worked in with CMA Contracting to overcome all obstacles, delivering the project with no elevated readings or Lost Time Injuries.

Project Facts
  • Over 40,000 tonnes of hazardous waste removed from sites
  • +4000 hours worked with zero ITIS or elevated readings
  • SafeWork NSW audited the site multiple times, zero non-conformances were raised.
What Our Clients Say

“CMA Contracting engaged Aztech Services Australia to work extensively as part of the Early Works Remediation Project at the former Smelter, Hydro Aluminium Kurri Kurri in Loxford, NSW. The works consisted of the rehabilitation of former farmland, rural properties and redundant landfill sites in land within the “buffer zone” of the former Smelter. This was an extensive rehabilitation program involving 25 individual sites, with rehabilitation completed over a 12-month period through 2018 and 2019.

Aztech provided a constant unwavering standard of safety and commitment to the undertaking all hazardous material works to the highest standard which contributed to a successful project delivery and ultimately the safe handing back of land which met EPA and Department of Environment and Planning rehabilitation standards. CMA have no reservations recommending Aztech for similar projects.”

CMA Contracting

More Projects