Built HQ, Sydney CBD, NSW

Location: Sydney, NSW
Client: 
McMahon Services Australia
Services: Asbestos Remediation
Value: $0.4 Million
Duration: August 2019

Project Details

Aztech Services Australia (Aztech Services) and McMahon Services (MCM) joined forces for Built to remediate and remove a friable asbestos contaminated roof on a heritage listed building in Sydney’s CBD.

During refurbishment works Built commenced removal of the building’s roof in preparation for the erection of a tower crane. During the roof removal, friable asbestos contamination and non-friable asbestos products were discovered.

Prior to the asbestos discovery, during the planning process, Built had scheduled a road closure to erect a tower crane on site. Aztech Services and MCM were the only contractors that could guarantee the completion of the remediation in time for the road closure and tower crane erection.

Innovative safety measures and removal methods were developed in full consultation with Built’s project and safety management team. Perimeter scaffold was erected and a roof structure was constructed over the existing roof. The roof level and level below were fully encapsulated and under negative pressure for the friable removal. Aztech Services and MCM completed works successfully, delivering the project 4 days prior to the road closure with no elevated readings or Lost Time Injuries.

Project Facts
  • Crane used for mobilisation of remediation plant and removal of waste
  • Over 2000 hours worked with zero ITIS or elevated readings
  • Project delivered 4 days ahead of program
What Our Clients Say

“Aztech Services Australia went beyond expectations providing an asbestos remediation solution for Built on the Refurbishment of their Head Office Building at 185 Clarence Street in Sydney. Aztech responded to the request for an urgent asbestos membrane removal on the roof of the building, which was being fully refurbished to almost the point of a new build.

With the installation of the Tower Crane, road closures and other trades booked Aztech excelled under pressure to remove the unexpected find of asbestos membrane. Aztech responded to the urgency of our request when others could not. Their expertise and approach were carried out without incident five days ahead of expectations. Aztech have a strong team of professionals both in-house and in the field. They were able to appreciate the urgency of the matter while not compromising their standards or legislative obligations for the Safe Removal of Asbestos in the heart of Sydney’s business district.”

Built